Question: On January 1 5 , 2 0 2 0 , Super Accountants Corporation purchased a parcel of land as a factory site for $ 2

 On January 15,2020, Super Accountants Corporation purchased a parcel of land

On January 15,2020, Super Accountants Corporation purchased a parcel of land as a factory site for $200,000. An old building on the property was demolished, and construction began on a new building which was completed on October 18,2020. Costs incurred during this period are listed below:
\table[[Demolition of old building,5,000],[Salvage value of old building,10,000],[Architect's fees,23,000],[Legal fees for title and contract,5,000],[Cost of natural grass,18,000],[\table[[Cost of digging the ground to make],[room for basement]],6,000],[Construction costs,\table[[800,00],[0]]]]
How much is the cost of the new building to be shown in the balance sheet?
842,000
829,000
818,000
824,000
as a factory site for $200,000. An old building on the property

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!