Question: On January 5 , 2 0 2 4 , a software company signs a contract to deliver a custom software application by July 1 5
On January a software company signs a contract to deliver a custom software application by July On March the software company informs the buyer that it is reallocating their resources to another project and wont be able to complete the software on time. Analyze this scenario by applying the rules of anticipatory repudiation of contract, adequate assurance of performance and substitute performance cover under the circumstances. What rights and damagesremedies would be available to the buyer?