Question: On July 31, 2018, Gilbert Construction issued a progress bill to Walker County for $1,900,000. The contract Walker County signed with Gilbert Construction was in

On July 31, 2018, Gilbert Construction issued a progress bill to Walker County for $1,900,000. The contract Walker County signed with Gilbert Construction was in the amount of $3,000,000. What is the journal entry to record the progress bill on the books of the county's capital project fund?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!