Question: Once a projects scope is established, it is never permitted to change, thus change control processes do not deal with project scope issues. True or

Once a projects scope is established, it is never permitted to change, thus change control processes do not deal with project scope issues.

True or False

2.

A good rule of thumb to use when creating work packages (the lowest levels of the WBS) is to make sure that every work package does exceed 10 days or two reporting periods in length/duration.

Group of answer choices

True

False

3.

The Work Breakdown Structure (WBS) should be output oriented and focused on the delivery of concrete (of substance) deliverables.

Group of answer choices

True

False

4.

The WBS is best suited for process-oriented projects, whereas a PBS is best suited for design and build projects that have tangible outcomes.

Group of answer choices

False

True

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!