Question: Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday). All activities require the same resource. Assume no working-day holidays during the months of May and Juneāno Memorial Day holiday, for example.
| Activity | Duration (days) | Predecessor |
| A | 5 | -- |
| B | 5 | A |
| C | 10 | A |
| D | 4 | A |
| E | 5 | B, C, D |
On a piece of scratch paper, draw the early-start Gantt Chart associated with this table. Assume the project is resource-constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Given that the Month of May has 31 days, what would be the completion date for the project?
Monday, June 8, 2020
Wednesday, June 10, 2020
Friday, June 5, 2020
Thursday, June 11, 2020
Thursday, June 4, 2020
Step by Step Solution
There are 3 Steps involved in it
To determine the completion date of the project well create an earlystart Gantt Chart based on the g... View full answer
Get step-by-step solutions from verified subject matter experts