Question: Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project

Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday). All activities require the same resource. Assume no working-day holidays during the months of May and June—no Memorial Day holiday, for example.

ActivityDuration (days)Predecessor
A5--
B5A
C10A
D4A
E5B, C, D


On a piece of scratch paper, draw the early-start Gantt Chart associated with this table. Assume the project is resource-constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Given that the Month of May has 31 days, what would be the completion date for the project?

  • Monday, June 8, 2020

  • Wednesday, June 10, 2020

  • Friday, June 5, 2020

  • Thursday, June 11, 2020

  • Thursday, June 4, 2020

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To determine the completion date of the project well create an earlystart Gantt Chart based on the g... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!