Question: One company has the process displayed below: a) What is the process time of the system? b) What is the process cycle time? c) If
One company has the process displayed below: a) What is the process time of the system? b) What is the process cycle time? c) If the firm operates 24 days per month, 6 days per week, 3 shifts per day, and 8 hours per shift, what is the weekly capacity of this process? 
B) A machine is designed to operate 3 shifts per day, 8 hours per shift, 7 days per week to produce 2000 units per shift. Set up and maintenance times have been estimated to be 15% of total time available for the machine. Actual output of the machine for one week has been 28000 units (5 Marks). Compute the following: 1. Design capacity of the machine per week 2. Effective capacity of the machine per week 3. The efficiency of the machine
Station 3A 4 units/hour Station 1 10 units/hour Station 2 12 units/hour Station 4 6 units/hour Station 3B 4 units/hourStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts