One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare
Fantastic news! We've Found the answer you've been seeking!
Question:
One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take into account that on hand, there are 40 units of Z, 70 units of A, 100 units of B, and 30 units of C. Also, there is a scheduled receipt of 20 units of component C in week 4. Lead times are two weeks for Z and B and one week for the other components. Lot-for-lot ordering will be used for all items.