Question: One way to leverage project audits to ensure that projects deliver on their value proposition is to logically organize a project into a number of

One way to leverage project audits to ensure that projects deliver on their value proposition is to logically organize a project into a number of sequential phases. At the end of each phase, an evaluation of the project determines whether the project should proceed, should be recycled (i.e., the current stage repeated), or should be terminated. This is known as ______.

A. project auditing

B. taking a stage-gate (also known as toll-gate or phase-gate) approach

C. project reserve analysis

D. conducting performance assessments for project team members

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The detailed answer for the above question is provided be... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!