Question: One way to prioritize addressing a process improvement gap is when what happens? A . The project is out of scope B . The standard

One way to prioritize addressing a process improvement gap is when what happens?
A. The project is out of scope
B. The standard deviation is greater than 2
C. A team member leaves the organization
D. Benefit exceed cost