Question: ones Company allocates manufacturing overhead based on machine hours. Each chair produced should require 3 machine hours. According to the static budget, the following is

ones Company allocates manufacturing overhead based on machine hours. Each chair produced should require 3 machine hours. According to the static budget, the following is expected to incur: 1,200 machine hours per month (400 chairs x 3 hours per chair) $6,000 in variable manufacturing overhead costs $8,400 in fixed manufacturing overhead costs