Question: ONLY SUBMIT NUMBER ANSWERS ( NO TEXT ) Material Requirements Planning _ ( MRP ) . What number should be placed in the spot presently

ONLY SUBMIT NUMBER ANSWERS (NO TEXT)
Material Requirements Planning_(MRP).
What number should be placed in the spot presently filled with the x?
\table[[Finished Product,SEP,OCT,NOV,DEC,JAN,FEB,],[,Gross Requirements,400,1,200,560,800,700,400],[,Schedule Receipts,,1,400,,,,],[,Planned Delivery,,,x,,800,480],[\table[[Projected on],[Hand],[Inventory]],\table[[Beginning],[Inventory =600]],200,400,1,040,240,340,420]]