Question: operates only one 8 hours shift per day and is scheduled to work 20 days next month (no overtime). Further, each station requires a 10%
operates only one 8 hours shift per day and is scheduled to work 20 days next month (no overtime). Further, each station requires a 10% capacity cushion. Click the icon to view the Cooper River Glass Works Flowchart. a. Which station is the bottleneck? The bottleneck is Station 2 , with a total load of 9500 minutes for the next month. (Enter your response as a whole number.) b. Using the traditional method, which bases decisions solely on a product's contribution to profits and overhead, what is the optimal product mix and what is the overall profitability? - x
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts