Question: Operation management question. please don't solve if you can't give the answers ( not guide ) , will dislike if you do it wrong or
Operation management question. please don't solve if you can't give the answersnot guide will dislike if you do it wrong or use chat gpt
The following table shows the summary activities for a construction project. Assuming that one
month is equal to
weeks answer the following questions:
table
Activity
IPA,Duration
weeks
Direct cost
$
A
B
A
SS
W
C
A
FS
W
D
C
FS
E
C
SS
B
FF
F
E
FS
D
FF
G
E
FS
A
Assuming that the project overhead is estimated to be $
and the yearly general
overhead for the contractor is estimated to be $
If the contractor distributes the
yearly general overhead over eight projects, the total direct cost is $
Draw the
expense curve
S
curve
for the project.B
Assume that the contractor is willing to use
profit
from the total cost
for this project.
Also, the contractor plans to submit his progress payment to the client at the end of each
month. Upon approval, the owner will deduct
for retainage
retention
and pay the
contractor one month later. The accumulated retainage will be paid with the last payment.
Calculate and draw the income profile
flow chart
and shade the overdraft area.;t The following table shows the summary activities for a construction project. Assuming that one
month is equal to
weeks answer the following questions:
table
Activity
IPA,Duration
weeks
Direct cost
$
A
B
A
SS
W
C
A
FS
W
D
C
FS
E
C
SS
B
FF
F
E
FS
D
FF
G
E
FS
A
Assuming that the project overhead is estimated to be $
and the yearly general
overhead for the contractor is estimated to be $
If the contractor distributes the
yearly general overhead over eight projects, the total direct cost is $
Draw the
expense curve
S
curve
for the project.B
Assume that the contractor is willing to use
profit
from the total cost
for this project.
Also, the contractor plans to submit his progress payment to the client at the end of each
month. Upon approval, the owner will deduct
for retainage
retention
and pay the
contractor one month later. The accumulated retainage will be paid with the last payment.
Calculate and draw the income profile
flow chart
hhbband shade ggthe overdraft area.
tableActivityIPA,Duration weeksDirect cost $ABASSWCAFSWDCFSECSS BFFFE FS DFFGEFS
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
