Question: Operation Number Work Center Setup Time ( Standard hours ) Run Time / Piece ( Standard hours ) Operation 1 0 1 2 1 .

Operation Number Work Center Setup Time (Standard hours) Run Time/Piece (Standard hours) Operation
10121.500.20 Turn shaft
20140.500.25 Mill slot
30170.300.05 Drill 2 holes
40030.450.10 Grind
50 Stores Inventory