Question: Operation X feeds into operation Y . Operation X has an effective capacity of 5 5 units per hour. Operation Y has an effective capacity

Operation X feeds into operation Y. Operation X has an effective capacity of 55 units per hour. Operation Y has an effective capacity of 50 units per hour. Increasing X's effective capacity to ensure that Y's utilization is maximized would be an example of ________ a constraint.
overcoming
cushioning
supporting
insourcing
outsourcing

Step by Step Solution