Question: Operations Management (BUSS-B 1006) - Summer 20- CW2 (Individual Assignment) - QP Part (B): (40 Marks) Given the following product tree (the quantities are shown

Operations Management (BUSS-B 1006) - Summer 20- CW2 (Individual Assignment) - QP Part (B): (40 Marks) Given the following product tree (the quantities are shown between brackets in the next page): A B(3) C(2) C(1) D(1) The following data for A, B, C and D is known: Stock Safety Stock Lot Size Lead Time A 10 0 20 1 B 30 0 50 2 0 0 1 1 D 0 0 400 The master production schedule calls for production of 15 A in period 1,5 in period 2, 15 in period 3, 10 in period 4, and 15 in period 5. There is a scheduled receipt of 20 A in period 1, 50B in period 2 and 90 C in period 2. 1. Calculate the MRP-explosion. 2. Compare between MRP and ERP. (30 Marks) (10 Marks)