Question: Operations management help needed, I will like or give thumbs up if answer is correct Three critical path activities are candidates for crashing on a
Operations management help needed, I will like or give thumbs up if answer is correct

Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. Which activity should be crashed first to cut two days from the project's duration; how much is added to project cost? Activity A; $6,000 Activity A;$8,000 Activity B; $10,000 Activity C;$4,000 Both A and C have to be crashed; $7,000