Question: OPERATIONS MANAGEMENT - PLEASE CLICK ON TO SEE ENTIRE PROBLEM JL.62 Durabrightwants to establish kanbans to feed a newly installed work cell for its line
OPERATIONS MANAGEMENT - PLEASE CLICK ON TO SEE ENTIRE PROBLEM
JL.62 Durabrightwants to establish kanbans to feed a newly installed work cell for its line of LED traffic signal lamps. The daily production (demand) rate for this new family of products is 60 units. The supplier lead time for the bulb housing, used by all products in this product family, is 11 days. They want to keep 1.5 days of safety stock of this housing on hand (the safety stock factor).
The kanban size for the bulb housing components is 67 units. How many kanbans do they require? (most appropriatewhole number.)