Question: Operations Management Spring 2 0 2 4 - Final Exam - Version B ( 8 Points ) A project engineer has created an AON diagram
Operations Management Spring Final ExamVersion B
Points
A project engineer has created an AON diagram for the relocation of the Styrofoam prom below. Please determine:
a The critical path of the project.
b The slack time between the various pathways
c The earliest start time and earliest finish time for activity F
d If $week is assigned to crash activity E if $ is spent to crash, what is t the project?
C
Start
B
G
Finish
D
H
E