Question: Operations Management Spring 2 0 2 4 - Final Exam - Version B ( 8 Points ) A project engineer has created an AON diagram

Operations Management Spring 2024-Final Exam-Version B
(8 Points)
A project engineer has created an AON diagram for the relocation of the Styrofoam prom below. Please determine:
a. The critical path of the project.
b. The slack time between the various pathways
c. The earliest start time and earliest finish time for activity F.
d. If $2000/week is assigned to crash activity E, if $4000 is spent to crash, what is t the project?
15
12
10
C
Start
B
10
G
35
Finish
D
H
40
10
E
24