Question: OPERATIONS RESEARCH Gil is a system engineer in KCA University. He has decided to install a new computer system to be used by the School
OPERATIONS RESEARCH
Gil is a system engineer in KCA University. He has decided to install a new computer system to be used by the School of Business. Gil has identified nine activities required to complete the installation.
The table below provides a summary of the activities durations.
Activities Time (weeks)
Optimistic Most likely Pessimistic
1 - 2 4 6 10
1 - 3 3 5 9
2 - 4 7 12 20
2 5 3 5 8
3 4 6 11 15
4 5 4 6 11
4 6 3 9 14
5 6 2 4 8
6 7 3 5 9
Required:
- The expected time and variance of each activity. [4 Marks]
- A project network for the activities. [4 Marks]
- The expected completion time and variance of the project. [2 Marks]
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock