Question: ops Supply Chain Managment Complete the MPS record below for a single item. (Enter your responses as integers. A response of 0 is equivalent to

ops Supply Chain Managment
ops Supply Chain Managment Complete the MPS
Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A January Quantity on Hand: 80 1 70 Forecast Customer 35 orders (booked) Projected on-hand Inventory MPS quantity 2 65 15 Order Policy: 100 units Lead Time: 1 week February 4 5 6 7 40 55 45 0 35 65 0 0 0 0 0 0 3 65 80 BE Week 80 55 50 0