Question: optimistic completion time, the most likely completion time, and the pessimistic completion time ( all in days ) for new contract are given in the

optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for new contract are given in the following table:
\table[[Activity,Time (days),\table[[Immediate],[Predecessor(s)]]],[a,m,b],[?bar(A),2,5,8,1],[B,4,5,6,-],[C,1,2,3,-],[D,6,7,8,C],[E,3,5,7,B, D],[F,2,3,a4,A, E],[G,5,9,14,A, E],[H,11,12,13,F