Question: Option # 1 : Wage Determination For this assignment, you will determine Davis Bacon wages for your area for brick and block work given the
Option #: Wage Determination
For this assignment, you will determine Davis Bacon wages for your area for brick and block work given the following scenario:
A crew of five carpenters and two laborers will be used to build formwork for a concrete structure. Work is scheduled for hours hrsday on Monday through Friday and hours on Saturday. Overtime at a rate of one and onehalf will be paid for all hours over hoursday on Monday through Friday and doubletime for all Saturday work. The base wage, taxes, and insurance rates are given below. Calculate the hourly, weekly, and monthly cost for the crew.
tableItemCarpenters,LaborersBase wage,$$