Question: Options are A) d b) E and G c) F D) D and H Save Answer As assembly line operates 8 hours per day with
Options are A) d b) E and G c) F D) D and H
Save Answer As assembly line operates 8 hours per day with a desired cycle time of 75 seconds. The task times and precedence relationships given below. Balance this line using the longest task time. What tasks would be assigned to workstation IV. Task Task Time (seconds) Immediate Predecessors Task Task Time Immediate (seconds) Predecessors A 30 E 15 B 35 65 C 30 A I 40 EF D 35 B 25 D G
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts