Question: OPTM 3 0 0 0 SP 2 4 EXAM ONE ( i Saved Help Save & Exit Submit This question will be sent to your
OPTM SP EXAM ONE i
Saved
Help
Save & Exit
Submit
This question will be sent to your instructor for grading.
A supplier of instrument gauge clusters uses a kanban system to control material flow. The gauge cluster housings are transported three at a time. A fabrication center produces approximately gauges per hour. It takes approximately three hours for the decided to ke replenished. Due to variations in processing times, management has decided to keep percent of the needed inventory as safety stock.
::
Required:
How many kanban card sets are needed? Round UP your answer to the next whole number.
eBook
References
Number of kanban card
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer