Question: OR 2 3 2 3 Midterm Examinations Problem # 1 Angeles Electric Corporation provides electric power for three cities. The company has four electric gensets
OR Midterm Examinations
Problem #
Angeles Electric Corporation provides electric power for three cities. The company has four electric gensets that are used to provide electricity. The main generator operates hours per day, with an occasional shutdown for routine maintenance. Three other gensets and are available to provide additional power when needed. A startup cost is incurred each time one of these gensets is started. The startup costs are $ for $ for and $ for
These gensets are used in the following ways: A generator may be started at : AM and run for either hours or hours, or it may be started at : PM and run for hours until : PM All gensets except the main generator are shut down at : PM Forecasts indicate the need for megawatts more than provided by the main generator before : PM and this need goes up to megawatts between : and : PM Genset may provide up to megawatts, genset may provide up to megawatts, and genset may provide up to megawatts. The cost per megawatt used per eighthour period is $ for $ for and $ for
Formulate this problem as an integer programming problem to determine the leastcost way to meet the needs of the area.
Problem #
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock