Question: or the case study in Question 1 , imagine you are the project manager. You have to keep control over the costs of the project.
or the case study in Question imagine you are the project manager. You have to keep
control over the costs of the project. Phase would take twentyfour months to
complete, and you are twelve months into it The partial structure of Phase is as follows:
MBOMBELA
STADIUM
PROJECT
A
B
ground works
Infrastructure
For A and B which are subaccounts of the Phase account, you have the following information:
Project
SubAccount
BCAC
ACWP
BQAC AQWP
Percentage
complete
BCWS
Original
Duration
OD
A
B
Calculate the following values, rounding to two decimals:
a
Earned value EV
A:
EV
B:
EV
b
Cost variance CV
A:
CV
B:
CV
c
Schedule variance SV
A:
SV
B:
SV
d
Schedule performance index SPI
A:
SPI
B:
SPI
e
Cost performance index CPI
A:
CPI
B:
CPI
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
