Question: or the case study in Question 1 , imagine you are the project manager. You have to keep control over the costs of the project.

or the case study in Question 1, imagine you are the project manager. You have to keep
control over the costs of the project. Phase 1 would take twenty-four (24) months to
complete, and you are twelve months (12) into it The partial structure of Phase 1 is as follows:
MBOMBELA
STADIUM
PROJECT
A
B
(ground works)
(Infrastructure)
For A and B, which are sub-accounts of the Phase1 account, you have the following information:
Project
SubAccount
BCAC
ACWP
BQAC AQWP
Percentage
complete
(%)
BCWS
Original
Duration
(OD)
A
150,00130,00115,00
120,00
80%
125,0024,00
B
130,00150,00
90,00
130,00
100%
130,0024,00
Calculate the following values, rounding to two (2) decimals:
a.
Earned value (EV)
(2)
A:
EV =?
B:
EV =?
b.
Cost variance (CV)
(2)
A:
CV =?
B:
CV =?
c.
Schedule variance (SV)
(2)
A:
SV =?
B:
SV =?
d.
Schedule performance index (SPI)
(2)
A:
SPI =?
B:
SPI =?
e.
Cost performance index (CPI)
(2)
A:
CPI =?
B:
CPI =?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!