Question: Order # Packaging Time ( days ) Job due date M 1 2 Day 1 3 M 2 4 Day 9 M 3 1 Day
Order
#
Packaging
Time days
Job due
date
M Day
M Day
M Day
M Day
The following dispatch list was generated for the packaging work center at the
beginning of day
Notes:
This is the final operation for each of these jobs
All dates represent the beginning of the day
The company works days a week
The standard queue time in packaging is days
All four jobs have just arrived in packaging
Determine the order schedule, mean flow time and mean lateness at the packaging work center based on the
following priority rules:
a Critical Ratio
b Slack per operations remaining
c First Come First Serve
d Shortest Operation Next
e Earliest due date job due date
f Earliest due date operations due date
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
