Question: Order # Packaging Time ( days ) Job due date M 1 2 Day 1 3 M 2 4 Day 9 M 3 1 Day

Order
#
Packaging
Time (days)
Job due
date
M12 Day 13
M24 Day 9
M31 Day 11
M45 Day 14
The following dispatch list was generated for the packaging work center at the
beginning of day 3
Notes:
This is the final operation for each of these jobs
All dates represent the beginning of the day
The company works 7 days a week
The standard queue time in packaging is 3 days
All four jobs have just arrived in packaging
Determine the order schedule, mean flow time and mean lateness at the packaging work center based on the
following priority rules:
a. Critical Ratio
b. Slack per operations remaining
c. First Come First Serve
d. Shortest Operation Next
e. Earliest due date (job due date)
f. Earliest due date (operations due date)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!