Question: Order Splitting Problem Units Day Ordered Capacity Required* (Minutes) 750 1050 960 Capacity Available (Minutes) 925 | 925 925 Utilization Over/(Under) (Minutes) Production Planner's Action
Units Day Ordered Capacity Required* (Minutes) 750 1050 960 Capacity Available (Minutes) 925 | 925 925 Utilization Over/(Under) (Minutes) Production Planner's Action 1 2 3 4 2 Total 25 35 32 92 New Production Schedule 92 3 4 5 6 Each part requires 30 minutes to produce.