Question: Oriole Construction is constructing an office building under contract for Cannon Company and uses the percentage - of - completion method. The contract calls for

Oriole Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion
method. The contract calls for progress billings and payments of $1350000 each quarter. The total contract price is $18738000 and
Oriole estimates total costs of $18000000. Oriole estimates that the building will take 3 years to complete and commences
construction on January 2,2024. At December 31,2024, Seasons estimates that it is 30% complete with the construction, based on
costs incurred.
By December 31,2025, Oriole estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred
has risen to $18600000 due to unanticipated price increases. What is the total amount of Construction Expenses that Oriole will
recognize for the year ended December 31,2025?
$8328600
$7878600
$13950000
$8550000
 Oriole Construction is constructing an office building under contract for Cannon

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!