Question: ou are given the following data for a project: Activity Expected Time (days) Critical A 15 YES B 4 NO C 10 YES D 8
ou are given the following data for a project: Activity Expected Time (days) Critical A 15 YES B 4 NO C 10 YES D 8 YES E 6 NO F 12 YES G 7 NO H 10 YES What is the expected completion time of this project? Group of answer choices 53 55 51 52 62