Question: OUESTION 1 [ 2 0 MARKS ] Answer all questions based on the information in Table 1 , pertaining to managing a project. ( a

OUESTION 1[20 MARKS]
Answer all questions based on the information in Table 1, pertaining to managing a project.
(a) Draw the precedence diagram AND calculate the total weeks to complete this project.
[5 Marks]
(b) In managing a project, you can deploy any of your employees to any of the activities in
order to shorten the activity path. Currently, you have Employee A who is working on
activity G meanwhile Employee B is under activity F. At the same time by fulfilling the
management required, you want to assign Employee A to help Employee B to shorten the
project duration. Every week, Employee A will help Employee B to working on activity G.
Unfortunately, as results, this activity delay by one week, meanwhile activity F need to
speed up by one week. Propose how many weeks should Employee A work on activity F
without delaying the project.
[15 Marks]
Table 1: Project data.help
 OUESTION 1[20 MARKS] Answer all questions based on the information in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!