Question: OUESTION 4 [ Total: 2 2 marks ] Joe has a building project that consists of nine activities. The activities that must be accomplished in

OUESTION 4[Total: 22 marks]
Joe has a building project that consists of nine activities. The activities that must be
accomplished in order to complete the project are listed as follows:
a) Construct a network diagram for this problem.
[6 marks]
b) Determine the expected time, variance, ES, EF, LS, LF and slack for each activity.
[9 marks]
c) Determine the critical path to complete the building project.
[1 marks]
d) What is the expected completion time of the building project?
[1 marks]
e) Calculate the variance of the building project.
[2 marks]
f) What is the probability that the project can be completed in 60 weeks or less?
[3 marks]A manufacturer produces three types of detergents, Ky, Lo and Mi. Each type of detergent
is produced using two machines, machine A and machine B. The following table gives the
information on the usage of the machines.
Due to the cost and manpower relationship, machine A must be used for at most 180 hours
while the maximum capacity for machine B is 240 hours. The profit obtained from each
unit of detergent Ky is RM53, from each unit of detergent Lo is RM62 and from each unit
of detergent Mi is RM75. The manufacturer wishes to know the quantity of each type of
detergent to be produced in order to maximize its profit.
a) Formulate the problem above as a Linear Programming Model.
b) Set up the initial simplex tableau by including the necessary slack variables. [Do
not solve until the final simplex table]
The optimal tableau for the above problem is given below, where x1 is Detergent Ky,x2 is
Detergent Lo and x3 is Detergent Mi,S1 and S2 are the slack variables for usage of Machine
A and Machine B, respectively.
c) State the optimal solution and the maximum profit.
d) Which of the constraint(s) are binding? Why?
e) If the cost required for an additional work hour for Machine B is RM4.50 per hour,
is it worth acquiring additional units of this resource? Explain your answer.
 OUESTION 4[Total: 22 marks] Joe has a building project that consists

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!