Question: OUESTION TWO: ( 5 MARKS ) Anticipated demands for a four - period planning horizon are 2 3 , 8 6 , 4 0 ,
OUESTION TWO: MARKS
Anticipated demands for a fourperiod planning horizon are and The setup cost is
$ and the holding cost is h$ per unit per period.
a What lot sizing do you obtain from the EOQ formula?
b Determine the lot sizes using the SilverMeal heuristic.
c Determine the lost sizes using the least unit cost heuristic.