Question: Our material plan for a given item shows that in Week 3 we have a scheduled Receipt (Order # 5325) of 600 units and a

Our material plan for a given item shows that in
Our material plan for a given item shows that in Week 3 we have a scheduled Receipt (Order # 5325) of 600 units and a Projected On Hand (POH) of 900 units. In Week 4 our material plan shows a POH of 800 units. Which of the following exception messages would be most likely to result? Defer Order #5325 so as to arrive in Week 4 O Expedite Order #5325 so as to arrive in Week 2 O Defer Order #5325 so as to arrive in Week 5