Question: Our project is now 50% through the execution stage. One of our suppliers has just announced that due to covid challenges in staffing, the raw

Our project is now 50% through the execution stage. One of our suppliers has just announced that due to covid challenges in staffing, the raw materials necessary for the completion of the project, which is a wedding planning of Mr and Mrs smith in the Maldives, will be delayed by 2 months unless a 25% premium is paid to an alternative supplier.

Who will be the Requestor in this project which is wedding planning?

We need to create a change request report that needs to consider all the impacts this recent request will have on the project. We need the following points to be described and explained briefly:

  • Detailed Description of Proposed Change
  • Justification for Proposed Change
  • Impact of changes on the scope
  • Impact of changes on the quality
  • Impact of changes on the requirements
  • Impact of changes on the cost
  • Impact of changes on the schedule
  • Impact of changes on the stakeholder
  • Projects documents
  • comments
  • Disposition
  • The justification for the changes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!