Question: our project team is creating a network diagram. Activity A (7 days) and Activity B (12 days) can start immediately. Activity C (3 days) can

our project team is creating a network diagram. Activity A (7 days) and Activity B (12 days) can start immediately. Activity C (3 days) can start after Activity A is complete. Activity D (4 days) and Activity F (3 days) can start after Activity B is complete. Activity E (5 days) can start after Activity C and Activity D are complete. Activity G (6 days) can start after Activity D and Activity F are complete. When Activity E and Activity G are complete, the project is done. If Activity D increases from 4 to 5 days, what is the critical path, and what is the length?