Question: Our static budget (put together before the fact) called for us to spend $22,000 on materials. Our flexible budget (put together after the fact) called
Our static budget (put together before the fact) called for us to spend $22,000 on materials. Our flexible budget (put together after the fact) called for us to spend $18,000 on materials. After the period ended, we discover that we actually spent $20,000 on materials, would this be a favorable or unfavorable variance?