Question: Over the previous three weeks a work center produced 36, 43, and 35 standard hours of work. What is the measured capacity? * 4 points
Over the previous three weeks a work center produced 36, 43, and 35 standard hours of work. What is the measured capacity? *
4 points
114 standard hours
36 standard hours
38 standard hours
43 standard hours
Cannot be determined with this data