Question: Overhead costs are underapplied if the amount applied to Work in Process is less than estimated overhead. less than actual overhead incurred. greater than actual

Overhead costs are underapplied if the amount applied to Work in Process is

less than estimated overhead.
less than actual overhead incurred.
greater than actual overhead incurred.
greater than estimated overhead.