Question: overhears this conversation and reports that the project will be late Later the project manager completes his own report saying, The project is still scheduled

overhears this conversation and reports that the project will be late Later the project manager completes his own report saying, "The project is still scheduled to be completed on time." Which of the following could be the reason the project manager made such a statement?
The activity has a mandatory dependency, allowing the project manager to place it in the project schedule at any location that he wants it to be done.
The activity has tree float and can be rescheduled later in its early-start to late-finish window.
The activity is on the critical path but is to be done after another activity that does have float.
The activity is on a near-critical path with less float than the length of the delay.
 overhears this conversation and reports that the project will be late

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!