Question: Overview: This assignment requires the use of MS-Project Software. Complete the assignment in accordance with the particulars provided below. Problem statement: Company A is responsible

Overview:This assignment requires the use of MS-Project Software. Complete the assignment in accordance with the particulars provided below.

Problem statement: Company A is responsible for conducting the project on the installation of new Security Product- Web Application Firewall, With START DATE AS 13TH September 2021. For better project output, they are using the Microsoft Project Software. Consider yourself as Project manager and create MS Project with following key project data with provided required duration and finalize the LAST DATE-

Key Points:

First summary point- Initiation

Discussion with service provider ---- 3 hours

Sub-Summary point- Defining and Planning

Background Investigation and Network analysis - 2 days

Identify Goals1 day

Research Previous experiences- 2 days

Develop strategies and plans- 1 week

Second summary point- Develop Preliminary project scope

Requirement list - 1 day

Determine the Scope --- 24 hours

Budget planning and approvals- 1 week

Select project team- 4 days

Third summary point- Design

Collect Information of all services offered- 3 days

Network Design for installation of new product- 7 days

Design database of all assets and servers- 4 days

Fourth summary point - Installation and Documentation

Deployment of Web application Firewall in the network- 4 weeks

Going live and testing of the firewall- 1 month

Audit all services, servers and assets with respect to risk - 2 weeks

Quality Assurance - 2 days

Documentation of all Process and Product Use CasesContinuous

Training and Handover- 5 days

Fifth summary point - Closing of project

Present the documented process to management and stakeholders-1 day

Assignment Questions:

a) Connect all task, as Next task will start after finishing previous task.

b) The task "Documentation of all Process and Product Use Cases" has to be performed for whole duration of "Fourth summary point - Installation and Documentation".So the start date for 1st task of Fourth summary point and "Documentation of all the Risks with respect to Cost" should be the same.

c) Change the Calendar setting as Monday to Friday as working days and Saturday, Sunday as holidays and time should be from 9am to 5pm. Take Screenshot for this time settings.

d) After every Summary point, add Milestone.

e) Study and save the Gantt Chart as well as MS project with .pdf format

f)Present your project overview using MS project overview feature take screenshot.

  1. Describe what you see in project overview.

g) Find deadline based on number of days given and specify the date.

Note- Submit two separate PDF by the due date:

  1. Your MS Project as specified in Question e)
  2. For questions c), f) and g).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!