Question: Overview: This assignment requires the use of MS-Project Software. Complete the assignment in accordance with the particulars provided below. Problem statement: Company A is responsible
Overview:This assignment requires the use of MS-Project Software. Complete the assignment in accordance with the particulars provided below.
Problem statement: Company A is responsible for conducting the project on the installation of new Security Product- Web Application Firewall, With START DATE AS 13TH September 2021. For better project output, they are using the Microsoft Project Software. Consider yourself as Project manager and create MS Project with following key project data with provided required duration and finalize the LAST DATE-
Key Points:
First summary point- Initiation
Discussion with service provider ---- 3 hours
Sub-Summary point- Defining and Planning
Background Investigation and Network analysis - 2 days
Identify Goals1 day
Research Previous experiences- 2 days
Develop strategies and plans- 1 week
Second summary point- Develop Preliminary project scope
Requirement list - 1 day
Determine the Scope --- 24 hours
Budget planning and approvals- 1 week
Select project team- 4 days
Third summary point- Design
Collect Information of all services offered- 3 days
Network Design for installation of new product- 7 days
Design database of all assets and servers- 4 days
Fourth summary point - Installation and Documentation
Deployment of Web application Firewall in the network- 4 weeks
Going live and testing of the firewall- 1 month
Audit all services, servers and assets with respect to risk - 2 weeks
Quality Assurance - 2 days
Documentation of all Process and Product Use CasesContinuous
Training and Handover- 5 days
Fifth summary point - Closing of project
Present the documented process to management and stakeholders-1 day
Assignment Questions:
a) Connect all task, as Next task will start after finishing previous task.
b) The task "Documentation of all Process and Product Use Cases" has to be performed for whole duration of "Fourth summary point - Installation and Documentation".So the start date for 1st task of Fourth summary point and "Documentation of all the Risks with respect to Cost" should be the same.
c) Change the Calendar setting as Monday to Friday as working days and Saturday, Sunday as holidays and time should be from 9am to 5pm. Take Screenshot for this time settings.
d) After every Summary point, add Milestone.
e) Study and save the Gantt Chart as well as MS project with .pdf format
f)Present your project overview using MS project overview feature take screenshot.
- Describe what you see in project overview.
g) Find deadline based on number of days given and specify the date.
Note- Submit two separate PDF by the due date:
- Your MS Project as specified in Question e)
- For questions c), f) and g).