Question: P-2) Nine jobs are to be processed through a single machine. The processing times and due dates are given in the following table. (65
P-2) Nine jobs are to be processed through a single machine. The processing times and due dates are given in the following table. (65 Pts.) Job 1 2 3 4 5 6 7 8 9 Processing 5 Time 6 4 2 8 6 5 4 5 Due Date 10 8 26 12 24 20 30 38 39 Furthermore, assume that the following precedence relationships must be satisfied: 26-3. 147-8. Determine the sequence in which these jobs should be done in order to minimize the maximum lateness subject to the precedence restrictions.