Question: P.4) Activity V on a critical path method network has predecessors T and U and successor W. V has duration 8, T's earliest finish is

P.4) Activity V on a critical path method network

P.4) Activity V on a critical path method network has predecessors T and U and successor W. V has duration 8, T's earliest finish is 21, while U's is 24. W's late start is 32. Determine which activity is critical and what is its slack. Show your detailed calculation. (5 pts.)