Question: PA 1 9 - 3 ( Algo ) Consider the AON graph of a project shown... Consider the AON graph of a project shown below.

PA 19-3(Algo) Consider the AON graph of a project shown...
Consider the AON graph of a project shown below.
Figure 19.18
The activity times are 3,5,3,7,7,1,3, and 2 days for activities A1 through A8, respectively. What is the earliest completion time of the project?