Question: PA 1 9 - 8 ( Static ) A project consists of 3 tasks, A , B , and C . . . . A

PA 19-8(Static) A project consists of 3 tasks, A, B, and C.... A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B and C are each dependent on A. B takes five days. C takes seven days with a probability of 0.5 and three days with a probability of 0.5. What is the expected completion time of the project?