Question: PA 18-12 to 1815 (Static) Processing times and due dates for five jobs... Processing times and due dates for five jobs are shown in the

 PA 18-12 to 1815 (Static) Processing times and due dates for

PA 18-12 to 1815 (Static) Processing times and due dates for five jobs... Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule. 12. What would be the lateness of job B ? weeks 13. What would be the tardiness of job E? weeks 14. What is the maximum tardiness for this set of jobs? weeks (Round your answer to 1 decimal place.) 15. What is the average flow time for this set of jobs? weeks