Question: PA 18-2 to 18-7 (Algo) Processing time for eight projects... Processing time for eight projects, displayed in the sequence they arrived. Project Processing time (hours)
PA 18-2 to 18-7 (Algo) Processing time for eight projects... Processing time for eight projects, displayed in the sequence they arrived. Project Processing time (hours) P1 5 P2 2 P3 2 P4 3 P5 7 P6 5 P7 1 P8 2.00 2. Given the projects displayed in table above, if FCFS is used to sequence the jobs what is the average flow rate of the projects? (Round your answer to 2 decimal places) projects per hour Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average flow time of the projects? (Round your answer to 1 decimal place) hours Given the projects displayed in table above, if FCFS is used to sequence the jobs what is the average inventory of the projects? projects Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is 2. the average flow rate of the projects? (Round your answer to 2 decimal places) projects per hour Given the projects displayed in table above, it FCFS is used to sequence the jobs, what is 3. the average flow time of the projects? (Round your answer to 1 decimal place) hours 4. Given the projects displayed in table above, if FCFS is used to sequence the jobs, what is the average inventory of the projects? (Use your rounded answers from Parts 2 and 3. Round your answer to 1 decimal place) projects 5. projects per hour Given the projects displayed in table above. If SPT is used to sequence the jobs what is the average flow rate of the projects? (Round your swer to 2 decimal places 6. Given the projects displayed in table above, SPT is used to sequence the jobs what is the average flow time of the projects? [hours (Use your rounded answers from Parts 2 and 3. Round your answer to 1 decimal place) Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average flow rate of the projects? (Round your answer to 2 decimal places.) projects per hour Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average flow time of the projects? (Round your answer to 1 decimal place.) hours Given the projects displayed in table above, if SPT is used to sequence the jobs, what is the average inventory of the projects? (Use your rounded answers from Parts 5 and 6 Round your answer to 1 decimal place.) projects