Question: PAD PRINTING ORDER LIST Job Date Order Received Setup Time Production Time Due Date 1 A 6 / 4 2 hrs . 6 days 1

PAD PRINTING ORDER LIST
Job Date Order
Received
Setup Time Production Time Due Date1
A 6/42 hrs.6 days 11 July
B 6/74 hrs.2 days 8 July
C 6/122 hrs.8 days 25 July
D 6/144 hrs.3 days 19 July
E 6/154 hrs.9 days 29 July
1Jobs are due at the beginning of their respective due dates.
Note: Setup time is to set up the pad printer at the start of the job. Setup includes
thoroughly cleaning the printing heads and ink reservoirs, installing the new pad(s) and ink
supply, and carefully aligning the machine. Setup at the beginning of a new day with the same
job is insignificant. What is the sequence using the EDD rule?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!