Question: Page 280Problem #7-14Using the following equations, graph the constraints, and solve using the corner point approach. Let:X1= number of air conditioners to be produced X2=
Page 280Problem #7-14Using the following equations, graph the constraints, and solve using the corner point approach.
Let:X1= number of air conditioners to be produced
X2= number of fans to be produced
Maximize profit = 25X1+ 15X2
subject to3X1+ 2X2<= 240 (wiring)
2X1+ 1X2<= 140 (drilling)
X1,X2>= 0